One of our most recent projects, a long standing client appointed us to undertake all the groundwork for an Olympic size riding school and stables to the very highest standard.  The school has been constructed to meet competition standard and this involved substantial earthworks, including:

Surveying and marking out the area required - 60 x 25 metres

Stripping the field and preparing the levels

Digging out and removing all clay to reach chalk

Installing a membrane and drainage

3000 tons of clean chalk acquired to level the school

1200 tons of clean single size limestone acquired for drainage and base

Instalation of fencing, kick-boards and gates

300 tons of track fibre surface material

All levelled to precise specification with 25mm tolerance throughout